Airport Improvements

Project Updates

Nearly $7 million in capital and major maintenance projects are scheduled at Bowman Field for FY 2011 through FY 2015. (The Authority’s fiscal year is July 1 through June 30.)

Here’s an update on some of the current projects:

Apron Upgrades

The apron near the Louisville Executive Aviation Hangar was rehabilitated. Additional apron repair and seal coating will be performed in 2012.

Central American Window Replacement 

New energy-efficient windows were installed in the Central American Airways office building in early 2011.

T-Hangars

A total of 32 new T-Hangars opened east of the Aero Club in late 2011. For T-Hangar lease and transition information, contact Darrell Watson at 502-363-8509 or darrell.watson@flylouisville.com

Asphalt Repair

Miscellaneous road repairs were made in 2011—including asphalt overlays on streets maintained by the Airport Authority.